Brookwood Elementary Gym Addition Taking Shape!

Fritz Wahlfield Construction

Updated: Mar 9, 2022

The gym addition at Brookwood is well underway. Sitework was done by Fischer-Idema Excavating and footings and foundations have been completed by VanLaan Concrete. JK Masonry is currently working to put up the CMU walls with Kerkstra Precast coming soon to put up the precast planks for the equipment mezzanine.




After spring break, VanDellen Steel will be erecting steel and Mugen Construction will be starting demo on the existing cafeteria and kitchen. Busy and exciting work is being done as we inch closer to summer and we work to be completed with this project before the 2023 school year begins.




POST CONTRIBUTED BY:


 
 
 